New
Link-Belt 100-ton RT slips into
tight spot
ROANOKE RAPIDS, N.C. (July
2002) — It is suppose to be a
textbook lift. The new 100-ton
capacity Link-Belt RTC-80100
Series II will pick a
prefabricated condenser unit from
a flatbed trailer and raise it to
a vertical position. Once off the
flatbed, the crane will rotate the
46,000-lbs., 50-ft tall, 12-ft
square structure more than 300
degrees and lower the unit onto
its foundation. However, what
looks good on paper isn't always
the reality. Several adjustments
will have to be made in order to
complete the lift.
Rocky Mount, NC-based Inco,
Inc. is contracted by the
Panda-Rosemary Water Company to
fabricate and erect a majority of
the new Panda-Rosemary plant in
Roanoke Rapids. The “out of the
ground” facility that is being
built on a “fast track” method.
Completion date is October 2002.
Panda-Rosemary Water is a
wholly owned subsidiary of Dallas,
Texas-based Panda Energy
International. It is being
designed and built to take
advantage of the secondary product
from the adjacent Panda-Rosemary
cogeneration facility. That is a
185-megawatt natural gas fired
plant built, at a cost of $140
million between 1989 and 1999, to
supply electricity to the Virginia
Electric Power Company under a
long-term contract.
Inco's project manager Chris
Sandlin, field superintendent
Ernest Jones, and crane operator
Carroll Selby had checked the
Link-Belt operations manual and
consulted with the facility
owner's representative to make
sure everything was ready. The
condenser unit would be a tight
fit. Not much room for error, but
well within the lifting limits of
the RTC-80100.
"The primary emphasis on any of
our jobs is safety. It might take
us a little longer, but we know
that a job will be done right when
an Inco crew makes a lift. The
safety of our men and the
customer's property are the most
important service that we provide.
The president of our company
wouldn't have it any other way,"
says Sandlin.
If the pick is any tighter,
Inco will need a drum of boom
grease to slip the crane into
position. The Inco crew slipped
their new Link-Belt RTC-80100
crane between an existing 48-ft.
high, 750,000-gallon water storage
tank and a hot (energized)
transformer grid. That's not all
that easy in a confined worksite.
A nearby trench containing
pipes connecting the new condenser
unit with the water storage tank,
and a soon-to-be-erected
evaporator could not be fully
compacted because the contractor
will install more process piping.
As in Murphy's Law, the trench was
in the worst conceivable place —
right under an extended outrigger
pad.
There never was a question as
to whether the new Link-Belt
100-ton RT could make the 24-ton
lift unassisted. The question is
whether the crane can be
positioned and makes the lift
without the possibility of
collapsing the trench. The
contractor filled and compacted
the trench. As an additional
safety precaution, the decision
was made to bring in a second
Link-Belt crane, an HTC-8670LB
“Long Boom”, to take part of the
initial load and force. This would
prevent any possible damaging tail
swing of the condenser unit during
the initial lifting phase.
"We probably could make the
lift, but we don't work that way.
It was the third of July and
everyone was looking forward to
the holiday. Why take a chance
with safety when we had the time
to do it right? We knocked off and
came back to work after the
holiday, bringing a Link-Belt
HTC-8670LB with us," said Sandlin.
The bottom line is that the
operator of the RTC-80100 safely
made the initial pick to lift and
load the condenser tower onto a
flatbed transporter by itself. A
second Link-Belt crane was brought
in as a safety precaution during
the erection pick. As soon as the
tower was raised to vertical, the
RTC-80100 completed the swing and
positioning of the new condenser
unit by itself.
Details of the lift include
picking and placing a tower that
weighs approximately 23-tons. The
on-board computer in the Link-Belt
RTC-80100 indicates an actual load
weight of 46,400 pounds. The
crane’s boom length is 95.2-ft, at
an angle of 70 degrees and a
working radius of just over 25
feet.
The operator of the HTC-8670LB
had more room to get into
position. He used a 30-ft. radius,
52 degree boom angle, with 58-ft.
of boom. At one time during the
erection, the Link-Belt HTC-8670LB
crane was lifting 19,500 lbs.,
making sure there was no extra
movement, and a plenty of
clearance from the water tower.
All of the units for this
plant, with the exception of the
760,000-gallon water storage tank,
are fabricated in the state of
Washington and trucked to North
Carolina. The companion evaporator
will be installed several weeks
after the condenser tower. In
between that time, Inco plans to
erect the dome top of the new
water tower with its RTC-80100
crane.
Completion was a day late, but
the job was completed without
incident and to standard. In fact,
the possibility of serious damage
was avoided. The soft, filled-in
compacted trench was reinforced
with large timber mats for the
outriggers. The two-crane lift was
performed without a hitch. The
helper crane was cut loose when
the load reached the vertical
position and the new RTC-80100
made the final swing and placement
unaided. |