Link-Belt LS-308H II and
LS-218H II are good dam cranes
UXBRIDGE, Mass. — Paris,
France-based Soletanche-McManus JV
recently marshaled two Link-Belt
lattice boom crawler cranes, the
LS-308H II and LS-218H II at the
West End Dam on the West River in
Uxbridge, Mass. The project’s
objective was to perform some much
needed embankment remediation,
according to Senior Project
Manager Michel Gavillet. Excess
seepage through the foundation of
the 2,400-foot long earth
embankment structure had been
detected as early as 1979. Several
previous attempts had been made to
stem the flow at the Corps of
Engineers' dam, all without
noticeable success.
"At times our progress is
measured inch by inch or minute by
minute. The boulders we encounter
are often harder to remove than
the solid rock. Soletanche is
using one of the most
technologically advanced earth
drills in the world. But we must
fall back on an old-fashioned
gravity-powered drop chisel
mounted on a new Link-Belt crane
to crush the rock before it can be
removed by the drill," said
Gavillet.
The joint venture would, for
the first time at the West End
Dam, construct a subsurface
concrete cutoff wall imbedded at
least two feet deep into bedrock
to assure complete water seepage
cutoff. The equipment spread
includes the piece of equipment
developed and constructed by
Soletanche specially designed for
deep and difficult slurry trench
excavation — the hydrofraise. The
hydrofraise contains a dredge type
pump located just above two
cutting wheels, to pump the
excavated materials, which are in
suspension in the bentonite
slurry.
A Link-Belt LS-308H II lattice
boom crane would break boulders
and the bedrock with the drop
chisel when the specialized drill
reached refusal. A second
Link-Belt crane, a LS-218H II,
would act as a combination
concrete placement tool and
service crane. About 75% of its
time was involved with concrete
placement. The LS-308H II would
also be a tool carrier equipped
with a special Soletanche-designed
clamshell bucket when excavating
the upper 15-ft. of the cutoff
wall trench. The hydrofraise could
not self-start the panel
excavation.
This specialized bucket was
also used to remove many of the
large boulders encountered when
drilling. Often these boulders
were clumped together into what
the senior project manager
referred to as boulder "nests".
"You need three cranes to build
a project like the one we have
here at the West End Dam in
Uxbridge, MA. We brought in our
own machine for the hydrofraise.
The other two Link-Belt cranes
were rented from Wood's CRW
Equipment Corp. for the length of
the job," added Gavillet.
Over 15,000 cubic yards of
poured-in-place concrete would be
required for the cutoff wall
construction. The 4,000-psi panel
concrete was trucked to the site
in ready-mix trucks. There was a
significant concrete quantity
(more than 20%) overage. The
original plans failed to include
the amount of extra concrete that
would be required to fill the
voids left by the boulder removal.
"Some of the panels required
twice the estimated amount of
concrete because of the voids left
by the removal of the boulders.
They have been a very significant
problem in the construction of the
cutoff wall," continued Gavillet.
This dam was implemented when
it became painfully obvious in
1955 that a series of new flood
control dams were needed to
protect Southern New England.
Hurricane Diane had deposited up
to twenty inches of rain over the
area and caused $540 million in
downstream flooding damage. That
became the impetus for the 1959-61
construction of the West Hill Dam
at a cost of $2.3 million.
As constructed, the 48-ft. high
earth fill dam would impound a
12,440-acre-foot reservoir. This
is the equivalent of storing four
billion gallons of water from an
upstream 27.9 square mile drainage
area. Normally West Hill is a dry
bed reservoir. However, during
flood events, its pool can cover
1,025 acres and extend upstream
for about 4.5 miles.
It was during flood events in
1979, 1987 and 1998 that excess
seepage through the structure had
occurred, prompting the need for
embankment remediation.
Gavillet said that their first
operation was to remove the top
ten feet of the dam and to
stockpile it for later
replacement. This provided a
larger work area for the equipment
spread and was done employing
typical earthwork methods. The
next procedure was to build twin
guide walls. Only then could the
construction of the paneled cutoff
wall begin. Work actually began in
August 2001. A hiatus was declared
during January and February 2002
because, due to subfreezing onsite
temperatures, the exposed
bentonite lines to and from the
Soletanche hydrofraise to the pump
would have frozen.
The cutoff wall was cast in
place by building a series of
alternating and interlocking
primary and secondary panels. Only
after the primary panels were
allowed time to cure could the
secondary panels be built.
"The total length of the cutoff
wall was about 1800 linear feet.
In between each two primary panels
was a secondary panel. The primary
panels were each 23-ft. long. The
secondary panels were 9-ft. long.
Both panels were 31.5-in. wide.
This is the width of both the
hydrofraise and the special
clamshell bucket. The deepest
cutoff panel was drilled down
123-ft.," explained Gavillet.
The granite Gneiss bedrock at
the West Hill Dam is up to 30,000
psi in hardness. The four chisels
used on the project were 31.5-in.
diameter, 15 to 20-ft. high and
weighed from 12 to 17 tons. Each
chisel would last approximately
three to four days under heavy
duty rock crushing.
A welder was then required to
spend at least a full workweek
rehabilitating the
manganese-cutting bar on the
bottom of the chisel.
All in all the rehabilitation
of the West End Dam was a very
challenging project. It required
the extensive technical knowledge
of Soletanche. It also required
the reliability and duty cycle
capability of two of Link-Belt's
newest conventional HYLAB lattice
boom cranes.
|