New Link-Belt crawler doubles Anderson Drilling's production
FULLERTON, Calif. (May 2002) — Lakeside, Calif.-based Anderson
Drilling, equipped with a new Link-Belt LS-308H II, recently completed the
drilling of 172 holes around the perimeter of a new luxury apartment
complex and parking garage in Fullerton, Calif. Anderson relied on its
recently acquired crane and a Watson model 5000 drill rig to meet the
project's stringent timeline.
"Our new Link-Belt LS-308H II, with its 90-ft. of boom and drill rig,
can just about double the production of our truck mounted drill rigs. It
allows our crew to use very long drilling tools (auger flights) to
increase production substantially. With the drill we are getting a torque
capacity of about 120,000 ft-lbs. That is plenty of power for what we
need," says Mike St. Germain, Anderson Drilling regional manager. The
difference between the crane mounted drill rig, and the production
Anderson anticipated to double their production with the new LS-308H II
versus a conventional truck-mounted drill rig. "Anderson Drilling buys
only top of the line equipment because of the demands we put on it. We
also modify it in our own manufacturing facilities to meet our exacting
standards.”
There was very little the general contractor could do until the
drilling contractor completed its work, and the job was already several
weeks behind schedule due to material arrival delay. At a pre-job
conference, St. Germain committed his company to helping Morgan's project
manager aggressively bring the job back into line with its overall
deadline.
This was no small task for Anderson who first moved its equipment on
the building site on a Thursday afternoon having pledged to have the job
completed and be off the site by the following Tuesday.
Anderson Drilling is a drilled shaft contractor, specializing in the
construction of both very large drilled shafts and large scope,
cast-in-drilled-hole (CIDH) concrete pile installations. They contract
work on very difficult or complex drilling sites. Their crews work when
there are extreme regulatory or environmental concerns and unusual design
installations.
"If you had to pick one specialty out of all the projects that we do,
it probably would be drilling very large diameter drill shafts. We have
the capability of drilling a 20 to 25-ft. diameter hole, 150-ft. deep. We
do this with a mobile, rubber-tired drill rig," explains St. Germain.
"On this job we are installing what is referred to as cantilevered
shoring piles to support the earth when the general contractor excavates
the area and builds a subterranean garage and apartment complex. We have
more than 170, 24 and 30-inch diameter shoring shafts to drill on
eight-foot vertical centers. Then we must place the steel beams in these
shafts for the lagging supports.
“These then must be imbedded in about 4 cubic yards of lightweight
concrete. The holes are spaced on eight-foot centers around the perimeter
of the project, which is approximately the size of one city block in
downtown Fullerton. Anderson Drilling has contracted for the entire
shoring project," continued St. Germain.
For the Fullerton project, Anderson is drilling in a sandy clay
material with a small amount of gravel. It is ideal for the utilization of
the long auger flights on a crane-mounted drill. From a production
standpoint, this type of soil presents the best working conditions.
With the Link-Belt LS-308H II, Anderson is able to cast this material
aside anywhere up to 180° from the hole being drilled. A front-end loader
with a blade box on the rear then spreads the material out smoothly and
incorporates it into the job site.
In a separate operation, a hydraulic service crane picks and places the
heavy steel beams in the drilled shafts while the Link-Belt crane
continues drilling. Finally, Anderson’s crew adds the correct amount of
concrete in each hole. There is no wasted motion; each operation
sequentially follows the one before it.
One of the major benefits of using the crane mounted drill rig is that,
unlike a smaller, rubber-tired drill, it allows Anderson to cast the
material a long distance away from the hole. This makes access by the
service crane and concrete trucks easier and faster. On a time critical
job like this, every minute counts.
The opportunity to sell this project hinged on the fact that Anderson
is able to meet Morgan's production requests and requirements. Anderson
relies on their new Link-Belt crane and its crew to help with that.
Anderson Drilling was not the low bidder for the job. But, in a series of
prebid conferences with Morgan, we were able to assure them that we could
do what they wanted done, when they wanted it done.
The LS-308H II Link-Belt crane saved our lunch on the project. I'm not
sure that the other bidders could do that," concluded St. Germain.
|