Reed & Reed celebrates 75th
anniversary in a big "bridge" way
Reed & Reed celebrated its 75th
anniversary by submitting
the award-winning bid to build a
new $10 million bridge over the Kennebec River in Augusta, ME.
Almost as if to put the final
candle on its birthday cake, the
company took delivery on a new
250-ton capacity Link-Belt LS-278H
crawler crane.
The high level bridge is a
five-span steel curved plate
girder with a concrete deck design
on a radius of 3000'. The girders
are fabricated of high performance
steel. It's 40% stronger and
tougher (more resistant to cracks
and weathers well). It will not be
painted.
This new technology benefits
the state by requiring less steel.
As a result the bridge costs less
to build and is easier to
maintain. This is only the second
project in the state to use this
type of steel.
Reed & Reed, one of northern
New England's foremost heavy civil
contractors since 1928, has also
been a long-term user of Link-Belt
cranes. From the start, they
established themselves as a leader
in Maine's bridge construction
industry. Over the years, they
have steadily expanded their
expertise. Today Reed & Reed
offers a full range of general
contracting services and have
about 16 Link-Belt cranes in
inventory.
Headquartered in Woolwich,
Maine, with regional offices in
the Caribbean, Reed & Reed now
performs a wide range of
commercial and industrial
construction. Projects include
highway and bridge construction,
marine facilities, hydro
facilities, heavy equipment
contracting, industrial buildings,
parking garages and environmental
remediation.
Reed & Reed President Jackson
Parker noted that this latest
crane acquisition was part of a
strategic move to further upgrade
and improve one of the largest
crane fleets in New England.
The new 250-ton Link-Belt LS
278H was shipped from the
Link-Belt factory in Lexington,
KY. The first of 11 truckloads
began arriving at the Kennebec
River Bridge project the first
week of July. By late the
following week, the delivery of
Reed & Reed’s newest crane was
complete. Erection commenced
immediately; a few days later, the
safety checks were complete, and
the machine was put to work.
The company has purchased five
new cranes in the past 3 years
including new LS-138H II (80 tons)
and LS-218H II (110 tons) crawler
cranes in 2000, a new RTC-8050
50-ton rough terrain crane in
2001, a newly rebuilt LS-418A (110
tons) crawler in 2002 and the
crown jewel of the fleet, the
brand new LS-278H 250-ton crawler
this year.
The crane will assist in
construction of the new Kennebec
River Bridge in Augusta, currently
under construction and scheduled
for a June 2004 completion. The
Maine Department of Transportation
awarded Reed & Reed the $10.8
million contract for the bridge in
January 2003.
Several other barge mounted
Link-Belt cranes, including an
LS-518 and an LS-418, are working
on the pier foundations. This
includes sheetpile driving for
cofferdam construction, excavation
and concrete pours.
The new high level Augusta
Third Bridge that carries Rte. 3
over the Kennebec River is 1105
feet long and 115 feet tall at its
high point. The two abutments and
four piers have a west to east
downslope orientation. The
poured-in-place concrete piers
range from 75' to 66' high. Crane
and bucket concrete placement was
carried out using Link-Belt
crawler cranes.
Each abutment has HP14 X 73
foundation piles in various
lengths that were driven to
refusal on bedrock. Pier #1 has
HP14X89 piles, also driven to
refusal. The other three piers
have spread footers resting on
bedrock. Pier 2 was excavated 30'
deep, Pier 3 - 12' deep, and pier
4 - 10' deep.
"A principal reason for the
purchase of the LS-278H crane
was not particularly for its
lifting ability, but for its
reach. We have one girder that is
120' long, 7.5' high, weighs
60,000 pounds and must be set out
90 feet. There's also a lot of
heavy hook work on this project.
Our pier and abutment formwork
requires a crane and operator with
very sensitive controls. When our
guys ask for a quarter or half an
inch, that's exactly what they
want," said Superintendent Greg Letourneau.
"That was the situation on this
pier. We have to lower the form
sections a half at a time once the
carpenters give us the word. The
first operation is simply to break
the gang form loose from the
concrete pier cap. Slow steady
pressure is the answer here. It’s
a matter of gently increasing the
pressure; you don't want any jerky
motion," said Operator Ralph
Rogers.
"There are men working up there
on scaffolding and you don't want
to endanger them. Then we lowered
the big panels with the single
whip line and swung 180 degrees to
put them down on the ground. At
that point, I was working out at
118' radius from the centerpin.
We're using regular lay wire rope
rather than the non-twist variety
because it gives us that little
extra safety factor. Besides, we
always have at least two tag lines
on a lift like this. We don't take
chances," added the LS-278H
operator.
It was interesting to note that
Rogers, a heavy equipment crane
operator for years, has worked on
three Reed & Reed Link-Belt
cranes, including the LS-518 and
an LS-218H. Seven years ago, he
also taught Jean Marie Burmeister
to operate the RTC-8050 that she
runs today.
Another task for the new
LS-278H is to place concrete for
the middle three piers using a
three cubic yard Gar-Bro concrete
bucket. That's a weight of about
24,000 pounds when fully loaded.
The crane will be operated from
the land trestle during these
procedures. The 278H has its work
cut out for it since there are two
concrete placements per shaft.
Concrete will be supplied by
Dragon Products Co. of Augusta.
"We literally had to pick up
that 80' X 8' plate girder form
for the pier cap a quarter inch at
a time in order to strip it and
lower it to the ground in two
pieces. There was a lower soffit
form underneath it and an angle
under that that gave us a very
limited space to let the jack down
on the falsework in order to get
that form out of there. We
literally had a total of only half
an inch to play with. The operator
used our new Link-Belt LS-278H
hydraulic crane to pick that
24,000 pound form up a quarter
inch at a time. That allowed us to
ease that form half out without
damaging the new concrete. Then he
could lower it down, back up, and
repeat the process to extract the
other form half. That's only the
beginning. The operator using that
crane is going to do that on three
more piers for a total of six
lifts," continued Superintendent
Greg Letourneau.
"The major difference between
the new LS-278H, of course, is
that the 518 is a friction crane
-- a great machine -- but a
friction crane never the less. Our
LS-278H is a state-of-the-art
hydraulic machine. This crane is
an operator's dream. I can sit in
it all day and go home at night
without feeling fatigued.
Originally, the reason I went from
the big 518 back to the 218H was
that I had knee surgery and
couldn't handle the legwork
required on the old friction
machines. With this new
250-ton Link-Belt with hydraulic
controls, everything is done with
an easy wrist motion. The cab is a
dream, great visibility and easy
access. And with the controls
configured the way the Link-Belt
engineers have done, it’s a smooth
-- very smooth -- crane. When the
guys up there ask for half an
inch, I know that I can give them
that with these hydraulics,"
concluded Ralph Rogers.
Chris Palmer, from Link-Belt
distributor CRW Corp., said, "Reed
& Reed keeps us on our toes on
this job, supporting their LS-418,
LS-518 and now the LS-278H. They
are really great people to work
with."
|