Chattanooga bridge expanded to six
lanes using Link-Belt cranes
CHATTANOOGA,
Tenn. (March 2001) —
Using three Link-Belt lattice boom crawler cranes, Britton Bridge Co. is
in the midst of a $26 million project to widen the U.S. Route 27 - State
Route 29 “Olgiati” bridge in Chattanooga spanning the Tennessee River.
Britton Bridge, a Mt. Juliet, Tenn.-based division of Jones
Brothers Co., is extending the bridge from four lanes, which includes two in each direction
with no shoulders, to six lanes — three in each direction with full
shoulders, with possible widening in the future. In an effort to restore a
vital link in its infrastructure, the State of Tennessee has elected to
rehabilitate the existing bridge across the Tennessee River near
Chattanooga.
“We closely studied the alternatives and decided that this
option would be economically feasible rather that adding a totally new
structure. We were further able to create a significant taxpayer dollar
cost savings by utilizing our own in-house design and engineering
forces,” said Ken Flynn, Assistant Area Regional Manager, Tennessee
Department of Transportation. The estimates to rehabilitate the existing
structure were approximately $26 million, versus the $35 million estimated
to design and construct another new bridge.
With this project, Britton Bridge faces two
distinct construction challenges. First, add to and widen the existing ten
land-based piers to support the new bridge configuration.

This is the conventional part of the project. Phase
two included extending the caps of the four massive water piers by adding
twin steel cantilever beams and shoulder bracing to each pier without
disturbing them or their foundations. Engineering tests had indicated that
the existing water piers would support the built-up steel plate girders
required to support the deck widening.
The eight cantilever beams (two for each water pier) are among the longest and
heaviest single pieces of steel fabricated for the job. They are 142 feet
long and weigh approximately 218,000 pounds each. These are shipped to the
job by rail where they are transferred to barges on the river and floated
into position. Two large, barge-mounted Link-Belt crawler cranes, a
250-ton capacity LS-278H and a 150-ton capacity LS-518, lift the massive
cantilever beams into position.
The 12-inch steel H-beam foundation support pile averaged between 30 and 60
feet long each. They are being driven to bearing, or refusal, depending
upon location with a Link-Belt LS-138H crane and a Delmag 3032-pile
hammer. Soil engineering borings showed a mix bag of common riverbank to
be driven through. Poured-in-place pile caps, pier foundations and land
columns were added and the varying height, six by six feet reinforced
columns are then formed and poured. New pier caps are formed and poured
and new structural steel was added for both the main bridge widening and
for interchange improvements.
For the water work involving hanging the steel, each Link-Belt crane is
mounted on a separate barge. The LS-278H is rigged with 160 feet of boom
with a six-part line, load block and a whip line. The LS-518 has a
150-foot boom, a six-part load line and a whip line. Because of strict
Coast Guard channel restrictions, Britton Bridge crews normally work
shifts from 7 a.m. until midnight several days a week when hanging the
transverse steel girders.
The steel erection, according to Jerry Britton, was facilitated by the use of
several man lifts, also working from barges.
In the past, skilled ironworkers would ride the load up, bolt it together and
walk across a four-inch wide flange two hundred feet in the air to bolt
the other end of the beam in place. Then they would likely slide down the
vertical flange to the ground only to start the procedure over again. It
was all part of the job, but done at an unacceptably high industry-wide
accident and injury rate. Because of new safety standards, technology and
a shortage of the old time ironworkers today’s skilled craftsman rides a
man basket to work, wearing a safety harness using an air impact wrench
instead of the traditional spud wrench.
The 11.3 million of structural steel was manufactured, fabricated and painted
by Carolina Steel Corp. of Montgomery, Ala. It was shipped to the bridge
jobsite by truck and rail. Some of the longest and heaviest transverse
girders are offloaded directly from the existing bridge deck after
temporarily closing down one lane of traffic. They are then lifted into
position by the barge mounted Link-Belt LS-278H crane. No steel erection
has ever begun until all steel is on hand for a full day’s work.
Because of the size and weight of some steel girders, they are fabricated in
sections and assembled in place utilizing both barge-mounted Link-Belt
cranes. A case in point is the haunch girders. They are erected one piece
at a time, each weighing approximately 102,000 pounds and being roughly 10
feet deep, and 137 feet long. When bolted together they would be too tall
for over the road transport and to heavy to erect as a single unit.
Utilizing both Link-Belt cranes, Britton Bridge, LLC was able to easily
achieve a balanced approach.
“We work very hard to achieve a safe, balanced lifting approach on every job
that we do. That’s just one of the many reasons for our fleet of a dozen
or more Link-Belt machines.
I would like to have two additional 250-ton capacity LS-278H cranes here,
but such is not the case, we only own one of them.
However, we do a lot of our own engineering on a project and
we knew that we could do all the work here with it and an older 150-ton
capacity Link-Belt LS-518,” explains Britton.
|