New Link-Belt crane and luffing attachment keeps juice from getting
loose in Florida
CLEWISTON, Fla. (February 2001) — Tropicana orange juice processing and storage
facilities in Fort Pierce and Clewiston are in the midst of a major
expansion of their facilities. With the help of two new Link-Belt 150-ton
lattice boom cranes, an LS-238H lattice boom crawler crane equipped with
the all new luffing attachment, and the recently introduced HC-238H II
lattice boom truck crane, the project is expected to be completed on time.
The contractor, Florida Atlantic, is renting the
two machines to fabricate refrigerated buildings to enclose 16 new orange
juice storage tanks at the Fort Pierce facility and four at the Clewiston
facility. Ft. Pierce currently has 52 tanks and Clewiston has 50. Each
building will cover a 120-foot by 120-foot footprint and enclose four,
53.5-foot diameter by 68-foot high storage tanks. Each tank stores up to
1.2 million gallons each of Florida’s finest. Each building will be
fully insulated to ensure the temperature of the juice is maintained at a
constant 34-degrees Fahrenheit.
Just how many oranges does it take to
fill a 1.2 million-gallon storage tank? Well, if it takes a 90-pound box
(approximately 160 pieces) of oranges to produce six and a half gallons of
orange juice. In order to fill one storage tank, it takes 29.5 million
oranges. Multiply that by the number of tanks the Ft. Pierce facility will
have after the expansion project, 68, and you will find that it will take
1.5 billion oranges to fill all the tanks with orange juice at the Ft.
Pierce facility alone.
Working room was very limited on both
jobs. The lay down yard was a bit closer for the HC-238H II equipped with
conventional boom. The HC-238H II truck crane had slightly more
maneuvering room than the crawler crane in the tighter working conditions.
"The crawler crane on the Ft.
Pierce project had to reach further, around, behind and over many more
tanks with approximately the same loads. We felt that this could be done
safer with a luffer because of the size of the tanks we had to maneuver
around,” said Steve Zeiger, president of Zeiger Crane Rental Co.
The tanks themselves rest on 3-feet
thick reinforced concrete slabs with approximately 6-feet of spacing
between each tank. It is in this space that the structural steel erector,
Florida Atlantic, is setting the steel, including the large panels, with
the two Link-Belt cranes. Seventy feet high by 20 feet wide fabricated
anchor panels are assembled on the ground and then lifted in place. These
are made from 14-inch I-beams. Each anchor panel weighs up to
18,000 pounds and is placed in strategic locations to fortify the columns
and bracing. These will support the walls and roofs of the new insulated
buildings. It will take the contractor’s eight-man crew approximately
four weeks to erect the 10-panels necessary to create the skeleton for
each building.
The Link-Belt cranes’ reach,
precision, accuracy and sensitivity are called for constantly. Line and
boom hoist speeds are also important assets. The steel is often being
placed out beyond the direct vision of the crane operator, with only a
six-foot space to maneuver between tanks. Precise control of the load is
critical.
Ron Luke is the operator of the
Link-Belt LS-238H crawler crane with the luffing boom attachment. The
crane is outfitted with a 90-foot luffing boom and a 140-foot luffing jib.
The luffing boom can boom down to 65 degrees with a working radius that
can reach well over 200 feet.
“With the luffing rig I can sit
closer to the tank foundations and consequently still reach out safely to
position the steel. I’m not certain how we could do it otherwise,”
said Luke.
Single lift load weights on the steel
at the Clewiston site range from about one thousand pounds to 16,000 to
17,000 pounds (large structural panels). Jay Stuart is the operator of the
Link-Belt HC-238H II truck crane with 200 feet of boom. The structural
support steel is erected outside of and then threaded in between the
tanks. Exterior walls and the roof will be added later. The tank
fabricators are on scaffolding applying special epoxy paint to the tank
exteriors as the structural steel is being put in place.
"Our cranes never
leave this yard without one of our operators on it. We are very proud of
our cranes; we maintain them in like new condition. In fact, if the
operator wants wax or other non-traditional maintenance supplies, we are
more than happy to pay for it. We work in a very hostile environment in
Florida, in addition to the sun and salt air, there is sand everywhere you
go in this state. And, as everyone knows, sand and heavy equipment do not
mix. On the other hand, the demand for orange juice is very good for the
health of our business," concluded Steve Zeiger.
|