Link-Belt crawler fleet proves to be sound investment for Alabama-based
bridge contractor
Lexington, KY (April, 2005) - “Probably the best example
of our 110 ton capacity LS-218H II would be a local emergency bridge
replacement that we just completed a few months ago. An 18-wheel tanker
truck, fully loaded with fuel exploded under a crossover bridge on the
interstate. The resulting fire was hot enough to melt the steel support
girders and totally destroy the structure,” said Vice-President Duncan
Morris.
“The ink was hardly dry on the Alabama DOT contract before we had
diverted our new Link Belt crane and rerouted it from another project.
The job had both a strict completion timeline and a very heavy
bonus/penalty clause. The completion timeline was for 63 days and either
way from this timeline, either incentive or penalty, the figure was
$50,000 a day. By working two 12-hour shifts around the clock, our
crews, relying on Link-Belts as the lead cranes, finished the job in
only 35 days. The total revenue on the job, including the early
completion bonus, was roughly $6.5 million,” he added.
In fact, the emergency bridge replacement project was actually
preceded with an eerily similar project only about two and a half years
earlier at almost the precise location. The Morris Group rebuilt that
bridge in 37 days under similar conditions and constraints with the aid
of its highly motivated crews and several other Link-Belt cranes.
The Morris Group, a Birmingham, AL.-based bridge contractor relies a
great deal on its fleet of modern heavy lift Link-Belt crawler cranes to
help make the transition from building structural steel bridges to the
currently more popular precast concrete structures, primarily with
driven pile or drilled shaft caisson foundations.
“By the very nature of our business, all the cranes in our equipment
spread must be dependable and multifunctional. We build bridges and
drive pile and our men and machines must meet different challenges every
week,” said Walter Morris, Sr.

“Initially I started the firm under my own name as a “dba” in 1987.
We incorporated as The Morris Group in 1991 after my sons, Walter, Jr.
(at left in photo above)
and Duncan (right) came onboard. The best description of our business is that we
are classified as a heavy and industrial contractor with primary
specialties in both bridge building and pile driving. Our major cliental
include state transportation departments and county and local
municipalities. In the private sector we serve industrial and commercial
accounts. A noteworthy amount of our work involves joint venture
contracts and major subcontracting operations with other contractors,”
he continued.
“We took a long time studying and testing what was available in the
marketplace before we purchased our first Link-Belt crane. We were well
aware that it would be a very large investment for a new company and we
wanted to make sure that we did it right the first time. We were so
happy with that machine that we decided to stay with Link-Belt cranes.
Since that time, we’ve built on that relationship and have stayed with
it.
"Back in the mid-1980’s there were a significant number of crane
manufacturers producing machines and many equipment dealers out there
selling them. The selection appeared almost endless. There were
Link-Belt, Lima, Bucyrus Erie, P & H, Koehring, American, Manitowoc and
others. It was imperative to us that the one we chose would still be
around in the future when we needed them for parts and service. It’s
interesting now to note that of the original group, only Manitowoc and
Link-Belt are still in business. To us it is very comforting to know
that our choice was and still is Link-Belt. We have gone through a few
dealers but now it’s Atlantic Southern, and we are pleased,” continued
the president and founder of the Morris Group.
“Unlike the old days, contractors use newer cranes on pile driving
operations. With the increased use of swinging or hanging leads, the
boom is isolated more compared to the older type fixed leads. This has
greatly reduced the shock and impact to the boom,” explained Vice-
President Duncan Morris.
The Morris Group uses its Link-Belt fleet for pile driving, concrete
pouring using the crane and bucket technique and prestressed beam
placement.
“We are building a pair of bridges in Russell County, Alabama. They
are part of the new four lane Rte. 431 Bypass that goes all the way into
Eufaula. Both 340’ long X 44’ wide bridges have 6’ diameter, 70’ deep
drill shaft foundations. Both of the four north and south abutments have
12” H beam pile foundations which were driven with a D-19 Delmag diesel
impact hammer using our new Link-Belt 218 HYLAB 5 crane. A load test
indicated that the required bearing would be reached using 25 foot long
pile. There were a total of 56 pile, or 14 for each abutment,” said
Nathan Black, a Morris Group Superintendent.

Going on to another Morris Group site, Link-Belt cranes were observed
again. “Our Link-Belt LS-218H II has played a large part in our safety
record on this bridge. The operator’s view from the cab is excellent and
that is important here because of its location. We are essentially
working the new bridge from each side of a deep valley and the men are
working at two different levels,” said Foreman Shane Sansom.
“We started the job at the end of December 2004 by demolishing the
old nine span bridge that was built in 1938 over Hatchet Creek in Coosa
County, Alabama.
"The new structure is a four span bridge. By eliminating five of the
columns, the creek will flow smoother and flood less. There were no
columns actually out in the creek itself. The new foundation consists of
4’ 6” drilled shafts. The upper shafts are 32 feet deep; the shafts down
in the valley are 14 feet deep. Russo, LLC, from Birmingham has
subcontracted the drilling and installation of these,” said Sansom.
On a third Morris Group bridge project in Jefferson County, Al., a
Link-Belt LS-138H II crane was outfitted with 100’ of stick, 80’ of
leads and a Delmag hammer for driving fourteen 30’ long 14” H pile for
the abutment foundations for the new Rte 79 bridge in Pinson, Alabama.
Superintendent Chris Brown said the piling was being driven to refusal
when they encountered rock.
Not untypical for the Morris Group, orders came down to pull the
Link-Belt crane off for a 24 hour period to drive several change order
piling at another nearby bridge project. The company has found this “go
anywhere, do anything” crane to be easily transportable enough to load
out, set up and return to its original project without causing a major
scheduling disruption. As Vice President Duncan Morris concluded, “just
another reason why we own and operate a spread of Link-Belt cranes,”
|