Dickinson
& Sons’ 218 HSL proves to be perfect fit
“The way this 218 HSL crane is set up gives the contractor both the
vertical height and horizontal reach that is needed. It acts like a
flattop tower crane without the logistical problems of putting down a
base foundation which would encounter a whole mess of underground
utility lines,” said Don Dickinson, the president of I.B. Dickinson &
Sons, Inc.
The requirement for this type of crane was brought about by the
uniqueness of the type of structure and the extreme space limitations
involved. The South and Spring Street Parking Garage, now under
construction in downtown Harrisburg, Pennsylvania, will be a 12 story,
755 vehicle parking garage with speed ramps for egress and exit. This is
a difficult construction project for a number of reasons. Not the least
of these is the limitation of space. There simply is no place for onsite
storage, not even a laydown area to shake out materials.
“We were able to reach a satisfactory arrangement for a long term
rental with I B Dickinson & Sons, Inc. from Reading, PA.,” said
construction manager, Gary Snyder. “The 110 ton capacity machine was
rented with fully qualified and experienced union operators who are
responsible for the crane’s day to day maintenance. Dickinson is also
accountable for performing the factory specified routine hourly
service."
“Essentially we are a crane rental house serving central and eastern
Pennsylvania,” said Don Dickinson, the president of I.B. Dickinson &
Sons, Inc. “The company was founded by my father, Irvin, 58 years ago.
Now my son, Jeremy, is also in the business, making us a three
generation family-run company. The smallest rental machine that we have
in our inventory is a six-ton boom truck and our largest is a 300-ton
capacity hydraulic crane. We have worked with this contractor several
times in the past and that makes it a lot easier.”
“A
very important part of our service is in supplying qualified operators
with our rental cranes. We rely on Local 542 of the Operating Engineers
for this and they have really upgraded their operator training program
lately,” added Don Dickinson.
“When the determination was made to go with this crane, the
availability of the luffing jib was a major consideration. It would be
very difficult to do this job as easily any other way. The 218 HSL
Link-Belt equipped in this luffer configuration is proving to be just
what we needed,” concluded Construction Manager Gary Snyder.
The consensus is that if a contractor had to design a crane
specifically for a job like this, they probably couldn’t do a better job
than Link-Belt has already done. The 218HSL, in the luffer
configuration, is a compact, maneuverable machine with a small
footprint, stability, reach and lift.
To cope with space limitations and crane capacity, the 218 HSL is
equipped with a total of 84,940 pounds of counterweight, including
11,100 pounds of sidetrack counterweight on each track.
“The
Link-Belt crawler crane is outfitted in the luffer configuration because
of the new garage’s unique placement. It is essentially an “infill”
structure being built on a vacant space surrounded by other high rise
structures. Space limitations ruled out the use of a larger conventional
or fixed mount tower crane. Fifteen foot wide alleys are adjacent to the
new building being built in the shadow of the magnificent state capitol
building. The parking structure is also situated over Spring St. which
is a point of entrance and exit to the garage,” said Project
Superintendent Jim Kellum for Pyramid Construction.
In the age of prefabrication and precast concrete lift panel
buildings, the new parking garage is primarily a cast-in-place concrete
structure. The foundation and lower floors are built relying on pumped
concrete placement. The columns and horizontal box beams on the upper
floors are all being placed using the tried and proven crane and bucket
technology.
A total of about 10,000 cu yds of cast-in-place concrete is required
for the overall project. The majority of this is 5,000 psi mix with a 7
day cure time. The exception here is that the post tensioning for all
the floors must be completed within the first 96 hours of the pour.
Concrete is being furnished by Pennsy Supply of Harrisburg and trucked
to the site on a carefully scheduled time basis to prevent a traffic
logjam in the downtown area. The Link Belt crane will be using a 1 cu.
yd. GarBro bucket for the crane and bucket pours.
Space
limitations also preclude the use, delivery and storage of precast
concrete panels or any other construction materials. The overall site is
bounded by Second Street, one of the busiest thoroughfares in this, the
state capital, as well as South Street and Susquehanna Streets.
“Traffic flow, including twice a day rush hours morning and night,
precludes our bringing in a series of trailers with precast concrete
panels. There simply is no space to park them, even on a temporary
basis. And just bringing in ready mix concrete trucks, one at a time to
the concrete pump, is a logistical nightmare.
“The crane is outfitted with a 130’ main mast and a 140’ luffer jib.
It was imperative that the crane have a level surface for the limited
area of travel available to it. For this we opted to bring in special
3-inch thick, lightweight Dura Base composite mats manufactured by The
Loma Company of Carencro, LA. rather than use the heavier, more massive,
conventional timber mats. We also added a layer of stone dust under the
mats and the results have worked well,” said Construction Manager Gary
Snyder.
“The new technology today demands a new type of operator. While it is
true that we still have the older printed capacity load charts, the
computers have significantly reduced our absolute dependence on them.
The new versions simply will not let you override them, assuming that
you were foolish enough to try. These are second and third generation
computers, much advanced and far more dependable than the first
computers that appeared in cranes. Don’t misunderstand me; we still
refer to the load charts, especially in the planning stages. But we are
in a totally different world today and Link Belt has been at the
forefront of this,” said operator Joe Mihalik.
“As might be expected, weather is also an important consideration.
The job commenced in April 2006 and completion is scheduled for around
July 2007. That allows for only a couple of snow days and maybe a couple
for the traditional Pennsylvania deer hunters. It’s a real tight
schedule. Since we are doing the bulk of our construction during the
winter months, ambient temperature is always a consideration and with
cast in place concrete pours, winter cures will be a problem. We’ll have
to tent the pour and heat it during the process. Once the pour is
finished we will employ a chemical cure to complete the job.
“And, because of the crane’s configuration, winter wind is another
significant consideration. Strong gusty winter winds whip through the
alleys like a wind tunnel. We can only have the boom in the air when the
winds are less than 25 miles an hour. To cope with this limitation we
have installed a Hirschman PRS-80EZ wireless anemometer wind speed
sensor with an in-cab readout. The transmitter unit is mounted on the
knuckle between the vertical mast and the luffer boom. We have already
encountered this situation and that is when you know for sure that you
have a skilled operator. When he can safely lower the mast and boom
without damage when a high wind suddenly whips up, as Joe Mihalik did,
it’s a very comforting feeling,” continued Snyder.
The 218 HSL is also used to “fly” the plywood forms between floors
before and after the concrete is cured and the forms are stripped by the
carpenters. The largest forms are 56’ X 4’ square box beam forms. These
weigh 7,600 pounds each. The heaviest single pick (lift), at over 10,000
pounds, will be the precast concrete stair sections.
During one major lift of four 20’ X 8’ plywood panel forms with 12”
wood braces, the 218HSL was lifting about 5,000 pounds at that time. The
tower boom was set in 80 degrees with the luffer at 45 degrees. It set
the forms at a 130’ radius at the opposite end of the garage from the
crane.
|